GATES-CHILI CENTRAL SCHOOL DISTRICT - PHASE IX
Services: Enhanced Clerking / Construction Management
Project Value: $52 Million
Scope of Work: The project included renovations and additions
to the High School, Middle School, and Elementary Schools:
|
Extensive renovation
to the High School including a new front entrance with atrium,
an 11,840 sq ft Library, a science wing with new labs
and guidance and career centers, and an olympic size poo
|
|
Renovations to the Middle
School library and kitchen
|
|
Additions to the Middle
School including athletic rooms, a new covered walkway and
front entrance, and a new entrance to the main lobby
|
|
Infrastructure and energy-saving
improvements to the Middle School and the five Elementary
Schools including roof repairs, lighting replacements, installation
of cogeneration equipment
|